Near Term Activities

  • West Bank Interceptor Work Plan is due to EPA July 30. This plan will recommend monitoring and evaluating the 15 mile pipe for condition and flow capacity. After approval by EPA, the work will begin to install approximately 29 flow monitors to evaluate seasonal flow conditions and the line will be inspected for defects.
     

  • Sewershed Prioritization Report due to EPA by September 30. This report will determine the factors and process of how the City will go about prioritizing the various sewersheds for near and long term work. 